SITE MEETING FOR CINSTRUCTION OF A TWIN HOUSE AT BUKAMBA H C lll

The District Chairperson LCV and Technical staff headed by the Chief Administrative officer held a site meeting at Bukamba HC3.

The site inspection was a result of the construction of a twin staff House.

The team comprised of the RDC, DHO.

The CAO appreciated the ongoing construction for the Twin staff House and further warned on delayed works which has tainted the image of the District. Some contractors drag to finish on time and end up rolling works in the next financial year which is irregular.

SITE MEETING AT BUYOBE HEALTH CENTRE II

District Heads touring the Ward under construction at Buyobe HCIl

The District chairman LCV, CAO, CFO and DHO held a site meeting for the construction of a general ward at Buyobe HC2.

The purpose of the meeting was to monitor the progress of construction. The contractor was behind schedule and the team which prompted the District leadership to fast track the construction progress.

The CAO was impressed with the workmanship and further urged the contractor to speed up to avoid money being swept back to the consolidated fund.

SITE MEETING BUSAALE

LCV KAYUNGA HON. MUWONGE ANDREW

The LCV Chairman, District Speaker and technical staff visited Busale HC2 as part of monitoring government projects.

The LCV appreciated the progress of the work done at the health facility.

The construction is now at roofing level, However the District Health officer advised the contractor to avail him with periodic reports for the site meetings.

Mr Okello Stephen who is the Hospital Chairperson told the contractor to always pay casual labourers coz they almost broke the facility fence due to delayed payment.

SITE MEETING BUYOBE HEALTH CENTRE II

The District Chairperson together with the District Speaker and technical staff conducted a site visit to Buyobe Health Centre 11.

The District team noticed that the construction works were on hold which annoyed the District Team.

The contractor raised issues of lack of financial capacity but promised to complete the work by May 2023.

The District Engineer warned the contractor against his flimsy excuses and urged him to be truthful to himself.