EXPANSION AND MAJOR RENOVATION OF KAYUNGA GENERAL HOSPITAL
Tuesday, 08 October 2019

A site meeting for the Renovation and expansion of Kayunga hospital has taken place at the hospital site. It started with a tour of the projects being worked on like the lagoon, , main administration block, theatre, private wards and staff quarters being renovated & newly constructed.
According to the report from the contractors , completed works was at 84.60% and anticipate to complete the project in February 2020.
Very soon block K1A & K1B will be handed over for use on Oder to pave for the renovation of the OPD and antenatal .