PROGRESS OF WORKS AT NSOTOKA HCIII
Tuesday, 06 February 2024
The district leadership held a site meeting for the construction of HCIII in nsotoka parish Kayunga subcounty.
The scope of work comprised of constructing a general ward, out patients department, 4 stance latrine, placenta pit, medical waste pit and external works.
The project was constructed by the UPDF engineers brigade at a cost of 837,310,381 million shillings which was cleared.
The overall progress of the work stood at 99% and the project was ready for commissioning.
The district leadership were so impressed by the quality of the work and promised to award more contracts to the engineering brigade.
The project will be handed over to KDLG on 8th day of February 2024.